Licensing Round Schedule

Activity Start Date End Date
Launch of the Intracampos Round September 11, 2018 September 11, 2018
Qualification of companies, acquisition of participation rights and implementation of on-site data rooms September 11, 2018 January 08, 2019
Study of Qualification Documents September 11, 2018 February 8, 2019
Publication of qualified companies February 11, 2019 February 15, 2019
Questions about the process and the bidding documents October 15, 2018 February 22, 2019
Responses to Questions by the Hydrocarbons Bids Committee October 15, 2018 March 1, 2019
Preparation, delivery and opening of tenders March 12, 2019 March 12, 2019
Submission of report by the Evaluation Committee March 12, 2019 April 2, 2019
Approval of the Evaluation Committee report by the Hydrocarbons Bids Committee Date of submission of the report April 9, 2019
Contract signing April 9, 2019 May 9, 2019