Licensing Round Schedule
Activity | Start Date | End Date |
---|---|---|
Launch of the Intracampos Round | September 11, 2018 | September 11, 2018 |
Qualification of companies, acquisition of participation rights and implementation of on-site data rooms | September 11, 2018 | January 08, 2019 |
Study of Qualification Documents | September 11, 2018 | February 8, 2019 |
Publication of qualified companies | February 11, 2019 | February 15, 2019 |
Questions about the process and the bidding documents | October 15, 2018 | February 22, 2019 |
Responses to Questions by the Hydrocarbons Bids Committee | October 15, 2018 | March 1, 2019 |
Preparation, delivery and opening of tenders | March 12, 2019 | March 12, 2019 |
Submission of report by the Evaluation Committee | March 12, 2019 | April 2, 2019 |
Approval of the Evaluation Committee report by the Hydrocarbons Bids Committee | Date of submission of the report | April 9, 2019 |
Contract signing | April 9, 2019 | May 9, 2019 |